Repair Water Storage Tanks

Repair Water Storage Tanks 2016-10-18T20:43:05+00:00

Project Description

This is a three-phase project to create a functional water storage solution at Barksdale AFB, Louisiana. In the first phase, TCL constructed a new 200,000-gallon water storage tank. Due to the soil conditions discovered by TCL, the tower was erected using drill piers and cast-in-place concrete. Phase two was the demolition of an existing elevated water storage tank that dated back to WW2, and complete restoration of the site. Phase three was a piping modification on a second existing tank in a high security area on the base.

Tunista Construction also performed site work including access drive, pipeline connections, splash pads, excavation, backfill, and grading.

Contract Number:  FA4608-14-C-0039

Owner:  United States Air Force

Location: Barksdale AFB, LA

Completion Date: December 2015

Contract Value: $1,960,800

Self-Performed Work: 18%

Delivery Method: Design-Bid-Build

Professional Services:

  • New Construction, Repair